Engineering & civil works

Land, Building & Civil Works

The Mixed use building has a total site area of 800 m2. The building floor area has covered 500 m2 and the remaining 300 m2 is left for other related construction. The type of buildings and its corresponding civil construction cost is given on Table 5.

List of Building & Civil Works and Their Costs

No Description Total price
A. Sub-Stricture
1
Excavation & Earth works
308,573.32
2
Concrete work
2,137,443.77
Sub total
2,446,017.09
B. Super Stricture
1
Concrete work
8,557,691.85
2
Block work
608,750.58
3
Roofing
188,858.74
4
Carpentry and joinery
357,346.86
5
Metal works
936,209.61
6
Finishing
3,434,153.93
7
Painting
304,410.25
8
Electrical installation
7,987,026.87
9
Sanitary installation
1,270,429.02
Subtotal
23,644,877.73
A+B
26,090,894.82
Vat (15%)
3,909,105.18
Grand total
30,000,000.00

As shown on Table 5, the total cost of building and civil work is estimated at Birr 30,000,000.00.