Project implementation

The project’s implementation is expected to take 12 months. The major activities include Bank loan processing construction of the building, cleaning the area around the building, Procurement of equipment and start rendering services. The time schedule for major activities is presented below:

SN Activities Date
1
Preparation Project Proposal
March 2022
2
Bank loan processing
May- June 2022
3
Site Development
July 2022
4
Building & construction work
July, 2022-June, 2023
5
Preparation for service
July, 2023
6
Service execution
February, 2024