Financial Requirement & Analysis

The financial resource is a prime resource for undertaking any activities. Hence for implementing this mixed use building a total of 48,000,000.00 ETB is required. From this 100% (48,000,000.00Birr) will be covered by the promoter of the project,no loan because it is a non- profit organization.

Therefore the said amount of finance is needed for undertaking the following.

Fixed Investment

A. Land, Building & Construction

S.N Description of works Total Cost in birr
1
Building construction
37,579,694.00
2
Site Development
69,200.00
3
Design and supervision
166,080.00
1st Year land lease
584,933.00
Total
38,399,907.00

B. Building Machineries and Equipment

S.N Description Measurement Qty Unit cost in Birr Total cost in Birr.
1
Generator
Unit
1
415,200.00
415,200.00
2
Carpentry tool box
Set
1
37,368.00
37,368.00
3
Electrician tools box
Set
1
25,604.00
25,604.00
4
Plumber tools kit
Set
1
17,023.00
17,023.00
5
Fire extinguisher (Security Equipment)
Unit
12
22,144.00
265,728.00
6
Elevator
Unit
1
600,000.00
600,000.00
Total
1,117,339.00
1,360,923.00

C. Vehicle

S.N Description UOM Qty Unit cost in Birr Total cost in Birr. Remark
1
Mini-Bus
Unit
1
215,200.00
215,200.00
Duty Free
2
4×4 wheel drive
Unit
1
200,000.00
200,000.00
Duty Free
Total
3
3
3
415,200.00
415,200.00

D. Office Equipment

S.N Description Measurement Qty Unit cost in birr Total cost in Birr
1
Managerial tables
Unit
1
10,080.00
10,080.00
2
Managerial chairs
Unit
1
15,600.00
15,600.00
3
Office table with chair
Unit
7
9,600.00
9,600.00
4
Secretarial table with chairs
Unit
1
6,800.00
6,800.00
5
Computer with chairs
Unit
1
12,000.00
12,000.00
6
Shelf
Unit
2,800.00
2,800.00
7
Filing cabinets
Unit
1
1,200.00
1,200.00
8
Guest chairs
Unit
1
3,920.00
3,920.00
9
Fax & Telephone machine
Unit
1
1,040.00
1,040.00
10
Carpet and Curtain
LS
1
18,400.00
Total
81,440.00

Working Capital

Operating Expenses

S.N List of Items Annual cost in birr Assumptions Used
1
Audit and legal fee
38,400.00
3200 br/per ,month
2
Stationery supplies
9,600.00
800 br/month
3
Promotional Cost
32,000.00
Lump sum annual cost
4
Property Insurance
67,207.00
1% of the building
5
Cleaning Supplies
9,600.00
800 br. Per month
6
Uniforms
9,600.00
7
Water consumption
4,000.00
1270 m3 by 3.15 br
8
Electric consumption
104,000.00
80,000KWH By Br.1.30
9
Fuel
30,400.00
1600 lit per year by Br.19
10
Telephone & fax
16,000.00
1333 per month
11
Repair expense
57,614.00
2% of building cost
12
Miscellaneous costs
32,000.00
2667 per month
Total
410,421.00

Pre-service Expenses

S.N Description Cost in birr
1
Project proposal
80,000.00
2
Licensing fee and others
Content
Total
80,000.00

Summary of Total initial investment cost

S.N Description Cost in birr Percentage Share
1
Land, building & construction
36,104,345.00
75.22%
2
Building machines & Equipment
1,798,923.00
3.74%
3
Vehicles
415,200.00
0.86%
4
Office Equipment
81,440.00
0.17%
5
Total fixed investment cost
38,399,908.00
79.99%
6
Salary expense
1,238,400.00
2.58%
7
Operation Expense
710,029.37
1.48%
8
Pre service Expense
80,000.00
0.17%
9
Total Working capital
3,019,342.63
6.29%
10
Sub total
43,447,680.00
90.52%
11
Contingency
4,552,320.00
9.48%
Total initial investment capital
48,000,000.00
100.00%